Planned maintenance and new developments

2019/2020 Planned upgrades

Last year, we spent over £2 million upgrading your homes to make them even better. The good news is we plan to continue to carry out planned repairs to your homes. Over the next 5 years we plan to spend £7.5 million on improving our stock and continuing to deliver our target of 750 new homes.

You can read below of the work we plan to carry out this year upgrading and improving homes for our tenants.

 

Sum of Budget (inc vat)      
Improvements Area No of Units Total
Bathroom Upgrades Thurso 14 £59,706
    32 £136,471
  Wick 22 £93,823
Bathroom Upgrades Total     £290,000
Heating Upgrades Aultbea 14 £171,613
  Dingwall 9 £110,323
  Inverness 4 £49,032
    13 £159,355
  Nethbridge 9 £110,323
  Poolewe 12 £147,097
  Tain 1 £12,258
Heating Upgrades Total     £760,000
Kitchen Upgrades Aviemore 1 £6,000
  Brora 1 £6,000
  Conon Bridge 6 £36,000
  Inverness 1 £12,000
    13 £78,000
    15 £90,000
  Nethybridge 10 £60,000
  Wick 2 £12,000
Kitchen Upgrades Total     £300,000
Window Replacements Invergordon 1 £5,141
    5 £25,704
    20 £102,817
    22 £113,099
    23 £118,240
Window Replacements Total     £365,000
Grand Total     £1,715,000